You bid one mobilization and drove out five times
The building slab made money and the sidewalks, ramps, and dumpster pad at the end took it back, eighteen months after you priced them.
The estimate gets built on total square feet, and total square feet assumes one setup without ever saying so. The closeout pours have the worst yardage to labor ratio in the trade, with short load fees applying under about 4 yards and demurrage exposure when a truck sits past the allowed unload time, so the smallest scope carries the highest unit cost and the most equipment per yard placed. Nothing in the bid separates the last trip from the first, so the loss on it stays invisible until the job closes.
The size of it
Four unbudgeted equipment moves at $1,200 to $2,500 each plus setup labor is $8,000 to $15,000 that was never in the number. The closeout trip is also where retention gets decided, so the least profitable mobilization controls whether the profitable one ever pays out.
Flatwork hits a job in three separate sequence positions, and the bid usually prices one. The building slab on grade goes early, right after foundations. Interior infill, housekeeping pads, and equipment pads come mid-build after MEP rough. Exterior flatwork, meaning the sidewalks, aprons, ADA ramps, curb, and dumpster pads, waits on underground utilities and paving and gets built at closeout, sometimes 12 to 20 months after the first trip. Every return moves the same iron: laser screed, ride-on trowels, saws, skid steer, forms, and a lowboy.
Three moves, in order
Step 02: Equipment cost basis
A true internal rate per machine covering ownership, maintenance, fuel, and transport, charged to the projects that used it.
What else costs concrete flatwork contractors money
The same mechanism in other trades
What concrete flatwork owners ask
How many mobilizations should i price on a flatwork bid?
The building slab made money and the sidewalks, ramps, and dumpster pad at the end took it back, eighteen months after you priced them.
What does it cost?
Four unbudgeted equipment moves at $1,200 to $2,500 each plus setup labor is $8,000 to $15,000 that was never in the number. The closeout trip is also where retention gets decided, so the least profitable mobilization controls whether the profitable one ever pays out.
What do I do first?
Count the mobilizations off the drawings before you price anything, and carry the move, the setup labor, and the short-load exposure as their own line for each trip.
What are concrete flatwork contractors supposed to be making?
Concrete flatwork runs 22% gross margin, 14% overhead and 8% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 1 points above it. The CFOS target is 10%.
Which part of the system fixes it?
The step is number 02, equipment cost basis. A true internal rate per machine covering ownership, maintenance, fuel, and transport, charged to the projects that used it. It comes from chapter 2 of CONTROL: The Construction Financial Operating System.
