CONCRETE FLATWORK · CONCRETE AND MASONRY · FIXED BY STEP 01

The 63 yards disappear between square feet and cubic yards

The slab came out at the thickness the drawings called for, you never got a change order, and you still bought and placed yards that weren't in the bid.

WHY IT IS A CONCRETE FLATWORK PROBLEM

Most trades buy and sell in the same unit. Flatwork is priced in area and purchased in volume, and the multiplier between them belongs to the sitework or utility contractor who set the grade. That makes another company's tolerance a direct line in your cost, and the only place it can be caught is on the day's delivery tickets.

WHAT IT COSTS

The size of it

At $165 per yard, 62 unbudgeted yards is roughly $10,200 on a single slab, before the placing and finishing labor to move it. Eight jobs a year like that add up to a five-figure monthly leak nobody in the office can account for.

OVERHEAD AT $1M–$5M
14%
CFOS target 13% for concrete flatwork.
GROSS MARGIN AT $1M–$5M
22%
CFOS target 23% for concrete flatwork.
NET PROFIT AT $1M–$5M
8%
CFOS target 10% for concrete flatwork.

You sell square feet of slab at a nominal thickness and you buy cubic yards at the plant, and the conversion between the two is set by whoever built the subgrade. A half inch of low grade across 40,000 square feet is about 62 extra yards, roughly a 10 percent yardage overrun. Nothing about that generates a change order, because the slab is the specified thickness and the square footage never changed. On a job cost report that codes concrete as one lump line, the overpour hides inside material cost and reads as margin fade with no cause attached to it.

WHAT TO DO

Three moves, in order

STEP 01
Split the concrete cost code into budgeted yards and overpour yards so the second one has its own line and its own dollar figure on every job cost report.
STEP 02
Shoot your own grade before the first load is ordered, then compare theoretical yards to ticketed yards the same afternoon, while the tickets are still on the truck seat.
STEP 03
When the grade comes in low, notify the GC in writing that day and price the added yardage before you pour, because after placement the evidence is under six inches of concrete.
QUESTIONS

What concrete flatwork owners ask

Why did we place more yards than we bid on a slab?

The slab came out at the thickness the drawings called for, you never got a change order, and you still bought and placed yards that weren't in the bid.

What does it cost?

At $165 per yard, 62 unbudgeted yards is roughly $10,200 on a single slab, before the placing and finishing labor to move it. Eight jobs a year like that add up to a five-figure monthly leak nobody in the office can account for.

What do I do first?

Split the concrete cost code into budgeted yards and overpour yards so the second one has its own line and its own dollar figure on every job cost report.

What are concrete flatwork contractors supposed to be making?

Concrete flatwork runs 22% gross margin, 14% overhead and 8% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 1 points above it. The CFOS target is 10%.

Which part of the system fixes it?

The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: The Construction Financial Operating System.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Josh Luebker ran commercial construction projects before he ran the numbers behind them, on data centres, military bases, hospitals, and high-rises. He wrote CONTROL: The Construction Financial Operating System, which is an eight-step framework for commercial subcontractors, and it publishes on October 1, 2026. He is a master electrician who moved into the office and kept the field vocabulary.

Sulphur Prairie Operations LLC maintains the benchmark reference behind these figures. Every edition is reconciled against the newest CFMA survey release before it publishes here. Where a figure changes between editions, the older edition keeps its year in the title so a citation to it stays correct.

Eight steps. Sixty days.

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It publishes on October 1, 2026. Eight steps, six working templates, and the order they install in.