You Finish First and You Get Paid Last
The tank has been holding water for eighteen months, the city loves it, and the owner still has your retainage.
Trades that finish near the end of a project wait weeks for retention. A tank goes up early and gets tested early because everything built after it depends on it, so the stretch between your last day of work and your last dollar is the longest on the job. You're also funding the next tank's plate package during that same stretch, which is how a shop with good margin still runs dry.
The size of it
On a $2.5M tank, 10 percent is $250K sitting for 18 to 24 months after your crew left the site, financed at your line of credit rate.
Your tank is on site four to ten months. The treatment plant, terminal, or industrial build it sits inside runs 24 to 36 months, and retention at 5 to 10 percent releases at substantial completion of the whole project, which is a different date than the day your tank passed test. Repaint and rehab work runs differently and ends the same way: eight to sixteen weeks of physical work, then the owner's engineer holds retention against a coating warranty that runs one to three years on an interior lining. Either way your money sits behind a clock that only starts once you've demobilized.
Three moves, in order
Step 07: Monthly cadence
Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month.
What else costs tank and vessel contractors money
The same mechanism in other trades
What tank and vessel owners ask
Tank subcontractor retainage held until plant completion?
The tank has been holding water for eighteen months, the city loves it, and the owner still has your retainage.
What does it cost?
On a $2.5M tank, 10 percent is $250K sitting for 18 to 24 months after your crew left the site, financed at your line of credit rate.
What do I do first?
Before you bid, read the retention clause and find the release trigger. Substantial completion of your scope and of the whole plant are two different dates and two different years.
What are tank and vessel contractors supposed to be making?
Tank and vessel runs 23% gross margin, 15% overhead and 8% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 1 points above it. The CFOS target is 10.5%.
Which part of the system fixes it?
The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: The Construction Financial Operating System.
