You Pay for Coupons Before You Bill a Weld
Four welders spent two weeks cutting and testing coupons, and none of that time had a job number behind it.
Most subs mobilize and start billing in the same week. A tank sub burns two to five weeks of engineering review plus a week of crew time on test coupons before a production weld exists to bill against. Because no billable milestone is attached, that spend almost always gets dumped into overhead, where it never posts against the job that caused it.
The size of it
You spend $3K to $10K in lab and third-party inspection fees plus a week of crew time before mobilization, and none of it comes back if the job pushes or dies.
Nothing gets welded until two approvals come through, and neither clock is yours. The tank design has to be PE-sealed and accepted by the owner's engineer, covering shell course thicknesses, seismic and wind calcs, anchor bolt loads, and foundation reactions. That same submittal is what the civil contractor needs to set anchor bolts, so you're gating another trade from day zero. Then WPS and PQR procedures and welder performance qualifications have to be qualified for the specific process, position, thickness range, and material, and plenty of owners want project-specific requalification that gets witnessed, with coupons sent to a third-party lab.
Three moves, in order
Step 01: Job cost structure
Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words.
What else costs tank and vessel contractors money
The same mechanism in other trades
What tank and vessel owners ask
Where to charge welder qualification and PE stamp costs on a tank job?
Four welders spent two weeks cutting and testing coupons, and none of that time had a job number behind it.
What does it cost?
You spend $3K to $10K in lab and third-party inspection fees plus a week of crew time before mobilization, and none of it comes back if the job pushes or dies.
What do I do first?
Open two cost codes on every tank job, one for PE submittal and engineering review and one for welder qualification, and charge coupons, lab fees, and inspection there instead of overhead.
What are tank and vessel contractors supposed to be making?
Tank and vessel runs 23% gross margin, 15% overhead and 8% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 1 points above it. The CFOS target is 10.5%.
Which part of the system fixes it?
The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: The Construction Financial Operating System.
