Base course in month two, retention released in month twenty
You place base and binder early so the site has something to drive on, then come back a year or two later for the surface. The bid carried one mobilisation.
Most subs finish their scope, punch out, and get released while the job is still moving. Paving is the trade whose scope is deliberately split across the entire schedule, so the money earned first is released last. The second trip also drags a full equipment package back to the site: paver, two rollers, a skid, a tack distributor, and lowboy moves, all charged against a single bid line that carried one mob.
The size of it
5 to 10 percent of the first billing sits locked up for the life of the job, and the return trip runs $3,000 to $8,000 of unrecovered cost that never becomes a change order because it was never priced as a separate mobilisation.
Paving mobilises twice on a building job and usually gets paid for one. Aggregate base and the binder lift go down early so the site has a working surface, then you leave and come back for the wearing course and striping after the building is finished, because the surface lift can't survive construction traffic. On a mid-size commercial build those two trips sit 12 to 24 months apart. Retention on the month-two billing isn't released until final acceptance of the whole project, and the GC won't close you out early because paving is one of the last items on the punch list.
Three moves, in order
Step 07: Monthly cadence
Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month.
What else costs paving contractors money
The same mechanism in other trades
What paving owners ask
When do I get retainage released on base course paved two years ago?
You place base and binder early so the site has something to drive on, then come back a year or two later for the surface. The bid carried one mobilisation.
What does it cost?
5 to 10 percent of the first billing sits locked up for the life of the job, and the return trip runs $3,000 to $8,000 of unrecovered cost that never becomes a change order because it was never priced as a separate mobilisation.
What do I do first?
Price the return trip as its own bid line with its own mobilisation dollars, so the surface lift trip is sold rather than absorbed.
What are paving contractors supposed to be making?
Paving runs 20% gross margin, 14% overhead and 6% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 1 points below it. The CFOS target is 10%.
Which part of the system fixes it?
The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: The Construction Financial Operating System.
