INTERIORS · INTERIORS AND FINISHES · FIXED BY STEP 01

Your Door Hardware Sits in a Crate for Nine Months

You cut the deposit on doors, frames, and hardware in the spring so hollow metal frames can stand before the walls close, and the leaves and closers sit crated until finishes.

WHY IT IS A INTERIORS PROBLEM

A framing sub buys studs and track, then installs them the week the truck unloads. Interiors has to buy finish hardware at framing time, because the frame and the leaf come off the same made-to-order submittal against an approved hardware and keying schedule with fire labels. That makes the package non-returnable and non-substitutable. Electrified sets routinely run 20 to 30 weeks, so you can't split the buy to match the two install dates.

WHAT IT COSTS

The size of it

On a $900K interiors contract the DFH package commonly runs $120K to $180K, and the money goes out long before it comes back in. You carry the single largest material buy in the contract for six to nine months on terms that came due back at frames.

OVERHEAD AT $1M–$5M
13%
CFOS target 12% for interiors.
GROSS MARGIN AT $1M–$5M
19%
CFOS target 22% for interiors.
NET PROFIT AT $1M–$5M
6%
CFOS target 10% for interiors.

The DFH package gets released early because hollow metal frames have to be standing before either side of the wall goes on. Frames are the cheap part of that order. Money sits in the leaves, closers, exit devices, electrified hardware, and access control prep, and none of that installs until finishes. You end up with one purchase order, one deposit, one supplier net-30 clock, and two install dates six to nine months apart.

WHAT TO DO

Three moves, in order

STEP 01
Split the DFH package across two cost codes on the day you issue the PO, putting frames, anchors, and prep on the framing phase and leaves, closers, and electrified sets on the finish phase.
STEP 02
Ask the supplier for staged billing tied to the two releases, and get a stored materials line into your schedule of values so crated hardware bills while it sits.
STEP 03
Put the hardware submittal approval date and the quoted lead time in front of the GC before the first draw, so the deposit date and the install date sit on the same page.
QUESTIONS

What interiors owners ask

Paying for door hardware months before hanging any doors?

You cut the deposit on doors, frames, and hardware in the spring so hollow metal frames can stand before the walls close, and the leaves and closers sit crated until finishes.

What does it cost?

On a $900K interiors contract the DFH package commonly runs $120K to $180K, and the money goes out long before it comes back in. You carry the single largest material buy in the contract for six to nine months on terms that came due back at frames.

What do I do first?

Split the DFH package across two cost codes on the day you issue the PO, putting frames, anchors, and prep on the framing phase and leaves, closers, and electrified sets on the finish phase.

What are interiors contractors supposed to be making?

Interiors runs 19% gross margin, 13% overhead and 6% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 1 points below it. The CFOS target is 10%.

Which part of the system fixes it?

The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: The Construction Financial Operating System.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Josh Luebker ran commercial construction projects before he ran the numbers behind them, on data centres, military bases, hospitals, and high-rises. He wrote CONTROL: The Construction Financial Operating System, which is an eight-step framework for commercial subcontractors, and it publishes on October 1, 2026. He is a master electrician who moved into the office and kept the field vocabulary.

Sulphur Prairie Operations LLC maintains the benchmark reference behind these figures. Every edition is reconciled against the newest CFMA survey release before it publishes here. Where a figure changes between editions, the older edition keeps its year in the title so a citation to it stays correct.

Eight steps. Sixty days.

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It publishes on October 1, 2026. Eight steps, six working templates, and the order they install in.