Peak Payroll and Peak Retention Hit the Same Quarter
You start in month 10 to 14 of an 18 to 24 month build and install most of your contract in the last stretch, which is when the withheld retention balance is at its highest.
Trades that work early finish their ramp and then collect retention while payroll is falling. Interiors gets the reverse. The ramp and the punch stack into the same 90 days as the biggest withheld balance. You're also holding the release date for everybody else's retention, because the building doesn't reach final completion until your touch-up, doors, and hardware punch is signed off.
The size of it
This is where an interiors sub misses payroll on a job it will ultimately make money on. Peak weekly labor spend and peak withheld receivable collide, and the money is furthest out when the burn is at its highest.
Your first day is often month 10 to 14 of an 18 to 24 month build, and 60 to 70 percent of the contract installs in the final quarter of the schedule as crews ramp from a few men to a floor by floor push. Retention at 5 to 10 percent comes off every draw, so the withheld balance is largest in the same weeks the labor spend is steepest. Final release is gated by final completion, and final completion is gated by the punch list, which is your own work. The retention created in those last 90 days gets released 60 to 120 days after that.
Three moves, in order
Step 07: Monthly cadence
Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month.
What else costs interiors contractors money
The same mechanism in other trades
What interiors owners ask
Payroll peaks right when retention balance is the highest?
You start in month 10 to 14 of an 18 to 24 month build and install most of your contract in the last stretch, which is when the withheld retention balance is at its highest.
What does it cost?
This is where an interiors sub misses payroll on a job it will ultimately make money on. Peak weekly labor spend and peak withheld receivable collide, and the money is furthest out when the burn is at its highest.
What do I do first?
Build a week by week labor spend curve for the final quarter of every job before you sign it, and plot the projected retention balance on the same chart.
What are interiors contractors supposed to be making?
Interiors runs 19% gross margin, 13% overhead and 6% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 1 points below it. The CFOS target is 10%.
Which part of the system fixes it?
The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: The Construction Financial Operating System.
