FIBER · ELECTRICAL AND TECHNOLOGY · FIXED BY STEP 06

Make-ready is months of cash out before a billable foot

You applied in the spring, wired make-ready money to the pole owner, and the transfers still aren't done while the bucket crew waits.

WHY IT IS A FIBER PROBLEM

Most subs wait on a general contractor who at least wants the job finished. You wait on a power company and a cable incumbent who hold no contract with you and have no deadline you can enforce, and neither of them has a reason to move your poles this month. You paid them first, which makes fiber one of the few places where a sub funds another utility's labor months before earning a foot of his own.

WHAT IT COSTS

The size of it

Make-ready checks and crew build-up go out months before the first billable aerial foot, and crews get shuttled to lower production filler work to stay fed. Cash leaves on the utility's calendar and comes back on the carrier's.

OVERHEAD AT $1M–$5M
15%
CFOS target 14% for fiber.
GROSS MARGIN AT $1M–$5M
22%
CFOS target 24% for fiber.
NET PROFIT AT $1M–$5M
7%
CFOS target 10% for fiber.

Aerial fiber runs a fixed sequence and you own almost none of it. You file the attachment application, the pole owner surveys, the make-ready estimate comes back, you pre-pay it, then power and telco move their lines or the pole gets replaced, and only then can your lasher touch it. FCC shot clocks are measured in months, and large pole orders get batched, so a three hundred pole route moves at the speed of the slowest attacher on it. By the time transfers finish you've already hired the crew, moved the bucket and the lasher, and sent money to the pole owner.

WHAT TO DO

Three moves, in order

STEP 01
Book each make-ready pre-payment as a job cost on the route it belongs to so that route carries its own cash timeline.
STEP 02
Keep a pole status log by pole ID with applied, surveyed, estimated, paid, transfers complete, and ready to lash, and review it monthly beside the route's cash position.
STEP 03
Give filler work its own work order and rate so the hours that keep the aerial crew fed never get charged to the route that isn't producing.
QUESTIONS

What fiber owners ask

How long does make ready take before we can lash fiber?

You applied in the spring, wired make-ready money to the pole owner, and the transfers still aren't done while the bucket crew waits.

What does it cost?

Make-ready checks and crew build-up go out months before the first billable aerial foot, and crews get shuttled to lower production filler work to stay fed. Cash leaves on the utility's calendar and comes back on the carrier's.

What do I do first?

Book each make-ready pre-payment as a job cost on the route it belongs to so that route carries its own cash timeline.

What are fiber contractors supposed to be making?

Fiber runs 22% gross margin, 15% overhead and 7% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits right on it. The CFOS target is 10%.

Which part of the system fixes it?

The step is number 06, project management. Billing dates, change orders, and notices, run as standards that hold without anyone chasing them. It comes from chapter 6 of CONTROL: The Construction Financial Operating System.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Josh Luebker ran commercial construction projects before he ran the numbers behind them, on data centres, military bases, hospitals, and high-rises. He wrote CONTROL: The Construction Financial Operating System, which is an eight-step framework for commercial subcontractors, and it publishes on October 1, 2026. He is a master electrician who moved into the office and kept the field vocabulary.

Sulphur Prairie Operations LLC maintains the benchmark reference behind these figures. Every edition is reconciled against the newest CFMA survey release before it publishes here. Where a figure changes between editions, the older edition keeps its year in the title so a citation to it stays correct.

Eight steps. Sixty days.

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It publishes on October 1, 2026. Eight steps, six working templates, and the order they install in.