CFOS for QuickBooks, coming January 2027See what you get
FIBERCFOS-06
FIBER · ELECTRICAL AND TECHNOLOGY · FIXED BY STEP 06

Make-ready is months of cash out before a billable foot

You applied in the spring, wired make-ready money to the pole owner, and the transfers still aren't done while the bucket crew waits.

WHY IT'S A FIBER PROBLEM

Most subs wait on a general contractor who at least wants the job finished. You wait on a power company and a cable incumbent. Neither has a contract with you or a deadline you can enforce, and neither has a reason to move your poles this month. You paid them first. That makes fiber one of the few places where a sub pays for another utility's labor months before earning a foot of his own.

WHAT IT COSTS

The size of it

Make-ready checks and crew build-up go out months before the first billable aerial foot. Crews get moved to lower production filler work to stay busy. Cash leaves on the utility's calendar and comes back on the carrier's.

OVERHEAD AT $1M to $5M
15%
CFOS target 14% for fiber.
GROSS MARGIN AT $1M to $5M
22%
CFOS target 24.5% for fiber.
NET PROFIT AT $1M to $5M
7%
CFOS target 10.5% for fiber.

Aerial fiber follows a fixed sequence, and you own almost none of it. You file the attachment application. The pole owner surveys. The make-ready estimate comes back and you pre-pay it. Power and telco move their lines or the pole gets replaced. Only then can your lasher touch it. FCC shot clocks are measured in months, and large pole orders get batched, so a three hundred pole route moves at the speed of its slowest attacher. By the time transfers finish, you've hired the crew, moved the bucket and the lasher, and sent money to the pole owner.

WHAT TO DO

Three moves, in order

STEP 01
Book each make-ready pre-payment as a job cost on the route it belongs to so that route has its own cash timeline.
STEP 02
Keep a pole status log by pole ID with applied, surveyed, estimated, paid, transfers complete, and ready to lash, and review it monthly beside the route's cash position.
STEP 03
Give filler work its own work order and rate so the hours that keep the aerial crew busy never get charged to the route that isn't producing.
QUESTIONS

What fiber owners ask

How long does make ready take before we can lash fiber?

You applied in the spring, wired make-ready money to the pole owner, and the transfers still aren't done while the bucket crew waits.

What does it cost?

Make-ready checks and crew build-up go out months before the first billable aerial foot. Crews get moved to lower production filler work to stay busy. Cash leaves on the utility's calendar and comes back on the carrier's.

What do I do first?

Book each make-ready pre-payment as a job cost on the route it belongs to so that route has its own cash timeline.

What are fiber contractors supposed to be making?

Fiber has 22% gross margin, 15% overhead and 7% net profit before taxes at $1M to $5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.

Which part of the system fixes it?

The step is number 06, project management. Billing dates, change orders, and notices, written as standards that work without anyone following up on them. It comes from chapter 6 of CONTROL: C.F.O.S. Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for fiber contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.

What a fractional CFO does for fiber contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

Updated

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.