You float the switchgear for a year before you bill it
Switchgear and transformers are quoted in weeks that turn into quarters. You buy early to protect the schedule and fund it on your own money.
Long lead equipment forces a choice with no good answer. Release the order early and you pay the deposit and progress payments, sometimes the whole unit, long before a pay application can include it. Wait for the schedule to firm up and the lead time pushes back your energization date. That's the one date the GC will hold you to. Either way the exposure is on your balance sheet. Stored-material billing only helps if the contract allows it and the owner honours it.
Three moves, in order
What CFOS does about it
Purchase orders, bills and open invoices from QuickBooks Online go into the 13 week cash forecast, so the deposit and progress payments show on the week they are paid. Stored materials are a billing line on the pay app, with retainage tracked. Whether the contract allows billing stored gear is a clause you check before award.
Who owns this: Controller and project manager.
At $8M, one switchgear order can use a good share of a month's cash. List each long lead item with its order date, payment terms and the date it must be on site. At $30M, the controller should review that list with the PMs every month.
90 days free, a 90-day money-back guarantee, and cancel anytime. It opens January 2027.
Research from another source
These figures come from another company's survey, not from Run On CFOS. Each one cites the report and the page.
Billd's 2026 National Subcontractor Market Report found 79 percent of subcontractors use supplier terms to buy materials, and 77 percent have supplier terms of 45 days or less.
Source: Billd, 2026 National Subcontractor Market Report, page 9 (survey of 623 respondents, published May 13, 2026).
The report's text says 77 percent and its chart for the same question reads 78 percent.
Step 07: Monthly cadence
Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month.
Other problems step 07 solves
Other things that go wrong
What owners ask
How do electrical contractors handle long lead time gear cash flow?
Switchgear and transformers are quoted in weeks that turn into quarters. You buy early to protect the schedule and fund it on your own money. Long lead equipment forces a choice with no good answer. Release the order early and you pay the deposit and progress payments, sometimes the whole unit, long before a pay application can include it. Wait for the schedule to firm up and the lead time pushes back your energization date. That's the one date the GC will hold you to. Either way the exposure is on your balance sheet. Stored-material billing only helps if the contract allows it and the owner honours it.
Which part of the system fixes this?
The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It's drawn from chapter 7 of CONTROL: C.F.O.S. Construction Financial Operating System.
Does this only happen in electrical?
Effectively yes, and that's why it has its own page. Electrical belongs to electrical and technology and has 9% net profit at $1M to $5M. The mechanism behind this problem has no real analog in the other 47 trades, so the general advice doesn't fit it.
Where do I start?
List every long lead item by job with its order date and payment terms alongside the date it has to be on site, so the float becomes a dated number you can plan against.
Can I fix this without touching anything else?
You can try, and it doesn't hold. Step 07 depends on step 03, overhead calculation and step 04, estimating system and step 05, software and bookkeeping alignment and step 06, project management. Install it ahead of those and it produces numbers the field won't trust, which is worse than the problem you started with.
