One Bridge Takes Five Move-Ins and Pays One Mobilization
A single structure takes four to six separate trips in and out. The contract pays mobilization once, usually capped, usually paid down against early progress.
A trade that stays on site until it finishes mobilizes once and demobilizes once. A bridge sub leaves and comes back because the structure itself forces the breaks in work, and every break means crane assembly and teardown, a lowboy move, a trailer, crew travel, and re-staking. The bid still carries one lump sum mobilization item covering the first trip.
The size of it
Four unbudgeted remobs at $8K to $25K each is a six figure hole on one structure, and it surfaces on the P&L as a labor and equipment overrun with no cost code that explains where it came from.
Bridge work doesn't hold continuous occupancy of the site. Foundations want a drill rig or a pile hammer and casing; substructure wants forms and a different crew. The girder set is a two to three day event with a big crane on it. Deck placement needs a screed and a finishing crew, then a cure window. Rail and joints follow, and approach slabs come later still. Between each phase sits a cure period, a DOT test break, or a delivery date you don't control. Widenings and stage construction add a full cycle per traffic phase on top of that.
Three moves, in order
Step 01: Job cost structure
Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words.
What else costs bridge contractors money
The same mechanism in other trades
What bridge owners ask
How do you get paid for remobilization on a bridge job?
A single structure takes four to six separate trips in and out. The contract pays mobilization once, usually capped, usually paid down against early progress.
What does it cost?
Four unbudgeted remobs at $8K to $25K each is a six figure hole on one structure, and it surfaces on the P&L as a labor and equipment overrun with no cost code that explains where it came from.
What do I do first?
Open a numbered move-in cost code for each planned mobilization on the job you're running now, and start charging lowboy, assembly, travel, and staking to it this week.
What are bridge contractors supposed to be making?
Bridge runs 22% gross margin, 15% overhead and 7% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits right on it. The CFOS target is 10%.
Which part of the system fixes it?
The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: The Construction Financial Operating System.
