STRUCTURAL STEEL · ENVELOPE AND STRUCTURE · FIXED BY STEP 02

Out of tolerance anchor rods bill you by the crane day

The crane is rigged at six in the morning, the rods are out of tolerance, and no one on that site wants to sign a ticket before your crew starts drilling.

WHY IT'S A STRUCTURAL STEEL PROBLEM

Your start date is controlled by a concrete sub's tolerance and your biggest daily cost is a rented machine that bills the same whether it moves or not. No other trade commits equipment of that size before the predecessor's work has been verified by anyone. That's why equipment cost on a steel job has to be coded by day and by job, so a standby day is visible the week it happens and not at year end.

WHAT IT COSTS

The size of it

Idle crane days plus a second mobilization run into tens of thousands on a mid size job. Unticketed, that cost goes to equipment with no job and no change order attached, and at month end it reads like your crane is too expensive.

OVERHEAD AT $1M–$5M
15%
CFOS target 14% for structural steel.
GROSS MARGIN AT $1M–$5M
23%
CFOS target 25.5% for structural steel.
NET PROFIT AT $1M–$5M
8%
CFOS target 11.5% for structural steel.

Erection can't start until foundations are cured, surveyed, and anchor rods are within AISC 303 tolerance. Your erector finds out of tolerance rods the morning the crane is rigged, because no GC gives you a survey of somebody else's concrete a week ahead. Crane rental bills by the day or the month with mobilization and demobilization each way, so an idle day burns at full rate against zero production. The fix, field drilling, repair plates, and EOR sign-off on the repair, is change order work, and it has to be ticketed while the crew is still on site or it gets absorbed.

WHAT TO DO

Three moves, in order

STEP 01
Require a written anchor rod survey from the GC before crane mobilization, and put the date you need it on the two week look ahead.
STEP 02
Give the foreman a standby ticket pad with the crane's daily rate printed on it and one rule: signed or photographed before the repair starts.
STEP 03
Code crane standby to its own cost code, separate from erection hours, so idle days appear as their own number in the monthly review.
QUESTIONS

What structural steel owners ask

Who pays for crane standby when anchor bolts are out of tolerance?

The crane is rigged at six in the morning, the rods are out of tolerance, and no one on that site wants to sign a ticket before your crew starts drilling.

What does it cost?

Idle crane days plus a second mobilization run into tens of thousands on a mid size job. Unticketed, that cost goes to equipment with no job and no change order attached, and at month end it reads like your crane is too expensive.

What do I do first?

Require a written anchor rod survey from the GC before crane mobilization, and put the date you need it on the two week look ahead.

What are structural steel contractors supposed to be making?

Structural steel runs 23% gross margin, 15% overhead and 8% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade is 1 point above it. The CFOS target is 11.5%.

Which part of the system fixes it?

The step is number 02, equipment cost basis. A correct internal rate per machine covering ownership, maintenance, fuel, and transport, charged to the projects that used it. It comes from chapter 2 of CONTROL: The Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, andCONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for structural steel contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, run by the same author.

What a fractional CFO does for structural steel contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.