Your work ends in March; your retention ends next spring
Shoring starts on day one of excavation, so your install is done in the first quarter. The retention rides until the whole project is accepted.
Every trade dislikes retention; what's different here is the span. You're the first trade on and one of the earliest done, so your retention is held across the longest possible stretch of any sub on that job. The last piece of your scope waits on another contractor's backfill, which means your completion date belongs to their schedule.
The size of it
Cash earned in month two sits until month eighteen, financed out of your line of credit while you're bidding the next three jobs.
No published benchmark reference breaks this trade out on its own. CFMA reports at NAICS level, and at that level this trade rolls into a broader bucket with several others. That's why this page carries mechanisms and no margin figures. It reports inside NAICS 238910 Site Preparation, so there's no shoring and shielding margin figure to put in this box. The 48 trades that do publish average 7% net profit at $1M–$5M before taxes, which is the nearest reference point worth anything here.
Your first day on site is essentially day one of excavation, and the install portion is complete very early in a civil or structure schedule. Retention is withheld against final acceptance of the entire project, not against completion of your work. The removal portion can't close out until the permanent work is built and backfilled, so you can't reach substantial completion of your own scope on your own effort, no matter how well your crews run. Money earned in month two gets financed by you until month eighteen, sitting on top of pay-when-paid on the progress billings themselves.
Three moves, in order
Step 07: Monthly cadence
Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month.
What else costs shoring and shielding contractors money
The same mechanism in other trades
What shoring and shielding owners ask
Shoring scope finished early but retainage held until the end of the project?
Shoring starts on day one of excavation, so your install is done in the first quarter. The retention rides until the whole project is accepted.
What does it cost?
Cash earned in month two sits until month eighteen, financed out of your line of credit while you're bidding the next three jobs.
What do I do first?
Build the cash plan by month on the calendar, not by percent complete. Mark the month your scope finishes and the month acceptance is forecast, and look at the distance between them.
Are there published benchmarks for shoring and shielding?
No, and this site won't print one. No published benchmark reference breaks this trade out on its own. CFMA reports at NAICS level, and at that level this trade rolls into a broader bucket with several others. That's why this page carries mechanisms and no margin figures. In the surveys it rolls into NAICS 238910 Site Preparation, so the closest honest reference is the 48-trade table, where net profit at $1M–$5M averages 7% before taxes. Read that as the neighbourhood, and read your own job costing as the answer.
Which part of the system fixes it?
The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: The Construction Financial Operating System.
