Your work ends in March; your retention ends next spring
Shoring starts on day one of excavation, so your install is done in the first quarter. The retention is held until the whole project is accepted.
Every trade dislikes retention. What's different here is how long it's held. You're the first trade on and one of the earliest done, so your retention is held longer than any other sub's on that job. The last piece of your scope waits on another contractor's backfill. So your completion date belongs to their schedule.
The size of it
Cash earned in month two stays until month eighteen, financed out of your line of credit while you're bidding the next three jobs.
Your first day on site is day one of excavation. The install part is done very early in a civil or structure schedule. Retention is withheld against final acceptance of the whole project, and finishing your own work doesn't release it. The removal part can't close out until the permanent work is built and backfilled. So you can't reach substantial completion of your own scope on your own effort, no matter how well your crews work. You finance money earned in month two until month eighteen. That comes on top of pay-when-paid on the progress billings.
Three moves, in order
Step 07: Monthly cadence
Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month.
What else costs shoring and shielding contractors money
The same mechanism in other trades
What shoring and shielding owners ask
Shoring scope finished early but retainage held until the end of the project?
Shoring starts on day one of excavation, so your install is done in the first quarter. The retention is held until the whole project is accepted.
What does it cost?
Cash earned in month two stays until month eighteen, financed out of your line of credit while you're bidding the next three jobs.
What do I do first?
Build the cash plan by calendar month. Mark the month your scope finishes and the month acceptance is forecast, and look at the months between them.
What are shoring and shielding contractors supposed to be making?
No survey separates shoring and shielding, so there is no figure of its own. The nearest comparable trade in the reference is Excavation, which has 21% gross margin, 14% overhead and 7% net profit before taxes at $1M to $5M, with a CFOS target of 10.5% net. Those are derived figures, not shoring and shielding's own. Read them as the neighbourhood, and read your own job costing as the answer.
Which part of the system fixes it?
The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It comes from chapter 7 of CONTROL: C.F.O.S. Construction Financial Operating System.
Everything on this page is something you can install yourself, and CONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for shoring and shielding contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, led by the same author.
