MASONRY · CONCRETE AND MASONRY · FIXED BY STEP 05

Block laid in month two, retention released in month twenty

You set structural block right behind the foundation, and the ten percent held on it stays untouched until substantial completion, a year and a half later.

WHY IT'S A MASONRY PROBLEM

Most trades earn where their retention is held, late in the job, so the hold and the work fall near each other on the calendar. Masonry goes vertical early and finishes late under a single number, which stretches the distance between earning and release further than any other subcontract on the building. The block scope alone can be held longer than some subs are even on site. Your estimator sees the bid margin and never sees the eighteen months the cash was gone.

WHAT IT COSTS

The size of it

On an 18 to 24 month building, ten percent of your largest and earliest revenue is unavailable for roughly eighteen months, while the labor that produced it went out the door weekly back in month two.

OVERHEAD AT $1M–$5M
14%
CFOS target 13% for masonry.
GROSS MARGIN AT $1M–$5M
21%
CFOS target 23.5% for masonry.
NET PROFIT AT $1M–$5M
7%
CFOS target 10.5% for masonry.

On a load-bearing CMU building the mason follows the footings, and structural block is usually the biggest single piece of the contract value. Then the same subcontract brings you back for veneer after dry-in, and back again for tuckpoint and cleandown at punch. The whole scope runs under one contract with one retainage account and one release at substantial completion. So your earnings pile up in the first third of the schedule while the release waits on the last day of the last third. The payroll that produced that block cleared the bank in month two.

WHAT TO DO

Three moves, in order

STEP 01
Build a retainage aging report keyed to the month the work was earned, not to the job, so you can see how old your oldest held dollar really is.
STEP 02
Negotiate a partial retention reduction on the structural scope at topping out, and do it during subcontract negotiation, not on a phone call in month fourteen.
STEP 03
Price block, veneer, and cleandown as separate lines on the schedule of values so the release conversation has three levers instead of one.
QUESTIONS

What masonry owners ask

How to track masonry retention when block is done a year before the job?

You set structural block right behind the foundation, and the ten percent held on it stays untouched until substantial completion, a year and a half later.

What does it cost?

On an 18 to 24 month building, ten percent of your largest and earliest revenue is unavailable for roughly eighteen months, while the labor that produced it went out the door weekly back in month two.

What do I do first?

Build a retainage aging report keyed to the month the work was earned, not to the job, so you can see how old your oldest held dollar really is.

What are masonry contractors supposed to be making?

Masonry runs 21% gross margin, 14% overhead and 7% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade is right on it. The CFOS target is 10.5%.

Which part of the system fixes it?

The step is number 05, software and bookkeeping alignment. Live job costs inside thirty seconds, with the bookkeeping cadence that keeps them current. It comes from chapter 5 of CONTROL: The Construction Financial Operating System.

OR HAVE IT HANDLED

Everything on this page is something you can install yourself, andCONTROL is the order to do it in. If you would rather buy the finished result, SPM The Construction CFO does this work for masonry contractors as a service. It is a separate firm, Sulphur Prairie Management, LLC, run by the same author.

What a fractional CFO does for masonry contractors

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Wrote CONTROL, the 8 step system behind these figures. More about the author.

8 Steps 60 Days

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It's out now. 8 steps, 6 working templates, and the order they install in. $9.99 ebook, $24.99 paperback.