SECURITY SYSTEMS · ELECTRICAL AND TECHNOLOGY · FIXED BY STEP 01

Warranty Starts at Ship Date, Yours Starts at Turnover

Gear bought in month six to beat lead times burns a year of manufacturer coverage before the owner ever accepts the building. Failures fall between the two clocks and you buy the part.

WHY IT IS A SECURITY SYSTEMS PROBLEM

Cameras, controllers, power supplies, and readers carry warranty measured from ship or purchase date, and on a 20 to 24 month build that clock runs while the gear sits in your warehouse and then in a ceiling. Your contract still owes a full twelve months from substantial completion, so the overlap you genuinely have shrinks every time procurement does its job well. This is the trade where the schedule fix and the warranty exposure are the same purchase order.

WHAT IT COSTS

The size of it

Every failure in that window costs you a truck roll plus a replacement part bought at full list. On a 120 camera job with normal infant mortality that runs into several thousand dollars of parts and a week of tech time charged to a closed job.

OVERHEAD AT $1M–$5M
16%
CFOS target 15% for security systems.
GROSS MARGIN AT $1M–$5M
22%
CFOS target 25% for security systems.
NET PROFIT AT $1M–$5M
6%
CFOS target 10% for security systems.

Fund a warranty reserve on every job at buyout, sized by how much manufacturer coverage you burned by buying early. The discipline that protects your schedule is the same discipline that wrecks your warranty position: the earlier procurement moves, the less coverage is left when the twelve month contractual clock starts at substantial completion. Nobody catches this at bid, because the exposure is created months later when a PM buys gear to hold a lead time. Record the manufacturer ship date on every serialized device at receiving so you know, per job, how many months of cover you own. Then either buy the extended term at PO or reserve for it out of the job that created it, so a month fourteen camera failure stops hitting a job that closed a year ago.

WHAT TO DO

Three moves, in order

STEP 01
Capture manufacturer ship date and serial number for every device at receiving and store it against the job, not just the PO.
STEP 02
At buyout, calculate coverage remaining at projected substantial completion and quote the extended warranty SKU whenever it falls under eighteen months.
STEP 03
Book a warranty reserve as a job cost at buyout so those failures hit the job that created them while it's still open.
QUESTIONS

What security systems owners ask

Camera manufacturer warranty expired before substantial completion?

Gear bought in month six to beat lead times burns a year of manufacturer coverage before the owner ever accepts the building. Failures fall between the two clocks and you buy the part.

What does it cost?

Every failure in that window costs you a truck roll plus a replacement part bought at full list. On a 120 camera job with normal infant mortality that runs into several thousand dollars of parts and a week of tech time charged to a closed job.

What do I do first?

Capture manufacturer ship date and serial number for every device at receiving and store it against the job, not just the PO.

What are security systems contractors supposed to be making?

Security systems runs 22% gross margin, 16% overhead and 6% net profit before taxes at $1M–$5M. The all-trade average is 7%, so this trade sits 1 points below it. The CFOS target is 10%.

Which part of the system fixes it?

The step is number 01, job cost structure. Seven cost categories and three levels of granularity, built so the estimate and the ledger use the same words. It comes from chapter 1 of CONTROL: The Construction Financial Operating System.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Josh Luebker ran commercial construction projects before he ran the numbers behind them, on data centres, military bases, hospitals, and high-rises. He wrote CONTROL: The Construction Financial Operating System, which is an eight-step framework for commercial subcontractors, and it publishes on October 1, 2026. He is a master electrician who moved into the office and kept the field vocabulary.

Sulphur Prairie Operations LLC maintains the benchmark reference behind these figures. Every edition is reconciled against the newest CFMA survey release before it publishes here. Where a figure changes between editions, the older edition keeps its year in the title so a citation to it stays correct.

Eight steps. Sixty days.

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It publishes on October 1, 2026. Eight steps, six working templates, and the order they install in.