THE PROBLEM · FIXED BY STEP 07

You don't have a WIP schedule

If someone asked today which open jobs are over and by how much, the honest answer would take a week to produce.

DIRECT ANSWER

The WIP schedule is the only report that tells you whether the work in progress is earning what you sold it for. Without one, you find out at closeout, which is the one point in a job where you can no longer do anything about the number. Every month you run without it, you're managing off the bank balance and a feel for how the jobs are going. Neither of those tells you a job is eating its margin while it's still open.

WHAT TO DO

Three moves, in order

STEP 01
Build the schedule from cost to complete, gathered from the people running the jobs.
STEP 02
Run it monthly at minimum, weekly on anything large or troubled.
STEP 03
Compare each job's current margin to the margin you bid it at.
QUESTIONS

What owners ask

Construction WIP schedule subcontractor?

If someone asked today which open jobs are over and by how much, the honest answer would take a week to produce. The WIP schedule is the only report that tells you whether the work in progress is earning what you sold it for. Without one, you find out at closeout, which is the one point in a job where you can no longer do anything about the number. Every month you run without it, you're managing off the bank balance and a feel for how the jobs are going. Neither of those tells you a job is eating its margin while it's still open.

Which part of the system fixes this?

The step is number 07, monthly cadence. Weekly bookkeeping, cost to complete, and one CEO report, on the same days every month. It's drawn from chapter 7 of CONTROL: The Construction Financial Operating System.

Is this normal for my trade?

Across the 48 trades in the benchmark reference, net profit at $1M–$5M averages 7% before taxes. If you're well under that and this page describes your month, the two are usually the same story. The published average tells you where the pack sits, and your own job costing tells you where you sit, which is the number that pays payroll.

Where do I start?

Build the schedule from cost to complete, gathered from the people running the jobs.

Can I fix this without touching anything else?

You can try, and it doesn't hold. Step 07 depends on step 03, overhead calculation and step 04, estimating system and step 05, software and bookkeeping alignment and step 06, project management. Install it ahead of those and it produces numbers nobody trusts, which is worse than the problem you started with.

AUTHOR
Josh Luebker
JOSH LUEBKER
MASTER ELECTRICIAN · 150+ PROJECTS · $2.1B+ MANAGED

Josh Luebker ran commercial construction projects before he ran the numbers behind them, on data centres, military bases, hospitals, and high-rises. He wrote CONTROL: The Construction Financial Operating System, which is an eight-step framework for commercial subcontractors, and it publishes on October 1, 2026. He is a master electrician who moved into the office and kept the field vocabulary.

Sulphur Prairie Operations LLC maintains the benchmark reference behind these figures. Every edition is reconciled against the newest CFMA survey release before it publishes here. Where a figure changes between editions, the older edition keeps its year in the title so a citation to it stays correct.

Eight steps. Sixty days.

CONTROL is the full system, written for commercial subcontractors from under $1M to $100M. It publishes on October 1, 2026. Eight steps, six working templates, and the order they install in.